无码少妇一区二区三区免费,妓院一钑片免看黄大片,国语自产视频在线,亚洲AV成人无码国产一区二区,激情久久综合精品久久人妻,日韩免费毛片,综合成人亚洲网友偷自拍,国内自拍视频在线观看,欧美熟妇性xxxx交潮喷,国产成人精品一区二免费网站

Africa  

Kenya set to complete 1st berth at Lamu port in December: official

Source: Xinhua   2018-07-06 01:58:29

LAMU, Kenya, July 5 (Xinhua) -- The first berth at the Lamu Port in Kenya's coastal region will be completed in December and not June as earlier announced, a Kenyan official said on Thursday.

The Lamu port is being constructed under an ambitious Lamu Port-South Sudan-Ethiopia Transport (LAPPSET) corridor project, an economic and transport corridor that stretches from Kenya's coastal Lamu port to South Sudan and Ethiopia.

Benson Thuita, the LAPSSET Corporate Affairs Officer, said completion of the berth has been pushed to the end of this year to ensure it meets international quality standards.

"A project of the LAPSSET's magnitude cannot be hurried. We expected the first berth to be completed by June but we are looking at the end of the year now," said Thuita.

He disclosed that construction of the first three berths which is fully financed by the government of Kenya, is ongoing with delivery times of 24 months of the first berth and 45 months for the next two at a cost of 480 million U.S. dollars.

"The first three terminals are coming with a capacity of 13.5 million tons. The container terminal can handle 1.2 million tones. The road from Isiolo to Moyale is already complete and in use, while that from Lokichar to the border with South Sudan is already under construction. So far so good," Thuita told Xinhua.

At the same time the government is structuring the remaining 29 berths to be concessioned to the private sector for construction and operations.

Thuita said the construction work for the first three berths is currently at a 46 percent completion rate. He was optimistic that the two other berths will be done and running by end of the year 2020.

Paul Maringa, the Principal Secretary in the ministry of transport said the government is committed to ensuring a speedy delivery of the 24.5 million dollars project, deemed the largest port in East and Central African region.

In the last East Africa Community (EAC) summit held in Kampala in December last year, LAPSSET was listed among the regional priority projects.

Sylvestre Kasuku, the Director General of LAPSSET, said it is no longer a project of Kenya, Ethiopia and South Sudan since the rest of the East African Community have adopted it.

"Key flagship projects are championed by presidents in Africa, and right now they are 10 in number. LAPSSET was the ninth admission, in 2015. The last was Walvis Bay in Namibia," said Kasuku.

"A recent review undertaken by Nepad, the AU secretariat and the UN Economic Commission for Africa realized that out of all these 10 projects in Africa, the best performing is LAPSSET," he added.

He noted that Kenya and Ethiopia have previously not had any land-linked infrastructure.

"Today, we have a road of 1,000km - Isiolo to Moyale and Moyale to Awasa - done by the two countries under the LAPSSET project. LAPSSET is ranked the global project of the year in opportunity creation not just for the African continent but the whole world," said Kasuku.

The LAPSSET project plan includes a 32-berth port, transportation hubs for rail, highway and international airports in Lamu, Isiolo and Lodwar, an oil pipeline from South Sudan, Uganda and Ethiopia to Lamu Port, an oil refinery and three resort cities in Isiolo, Lamu and Turkana.

Editor: yan
Related News
Home >> Africa            
Xinhuanet

Kenya set to complete 1st berth at Lamu port in December: official

Source: Xinhua 2018-07-06 01:58:29

LAMU, Kenya, July 5 (Xinhua) -- The first berth at the Lamu Port in Kenya's coastal region will be completed in December and not June as earlier announced, a Kenyan official said on Thursday.

The Lamu port is being constructed under an ambitious Lamu Port-South Sudan-Ethiopia Transport (LAPPSET) corridor project, an economic and transport corridor that stretches from Kenya's coastal Lamu port to South Sudan and Ethiopia.

Benson Thuita, the LAPSSET Corporate Affairs Officer, said completion of the berth has been pushed to the end of this year to ensure it meets international quality standards.

"A project of the LAPSSET's magnitude cannot be hurried. We expected the first berth to be completed by June but we are looking at the end of the year now," said Thuita.

He disclosed that construction of the first three berths which is fully financed by the government of Kenya, is ongoing with delivery times of 24 months of the first berth and 45 months for the next two at a cost of 480 million U.S. dollars.

"The first three terminals are coming with a capacity of 13.5 million tons. The container terminal can handle 1.2 million tones. The road from Isiolo to Moyale is already complete and in use, while that from Lokichar to the border with South Sudan is already under construction. So far so good," Thuita told Xinhua.

At the same time the government is structuring the remaining 29 berths to be concessioned to the private sector for construction and operations.

Thuita said the construction work for the first three berths is currently at a 46 percent completion rate. He was optimistic that the two other berths will be done and running by end of the year 2020.

Paul Maringa, the Principal Secretary in the ministry of transport said the government is committed to ensuring a speedy delivery of the 24.5 million dollars project, deemed the largest port in East and Central African region.

In the last East Africa Community (EAC) summit held in Kampala in December last year, LAPSSET was listed among the regional priority projects.

Sylvestre Kasuku, the Director General of LAPSSET, said it is no longer a project of Kenya, Ethiopia and South Sudan since the rest of the East African Community have adopted it.

"Key flagship projects are championed by presidents in Africa, and right now they are 10 in number. LAPSSET was the ninth admission, in 2015. The last was Walvis Bay in Namibia," said Kasuku.

"A recent review undertaken by Nepad, the AU secretariat and the UN Economic Commission for Africa realized that out of all these 10 projects in Africa, the best performing is LAPSSET," he added.

He noted that Kenya and Ethiopia have previously not had any land-linked infrastructure.

"Today, we have a road of 1,000km - Isiolo to Moyale and Moyale to Awasa - done by the two countries under the LAPSSET project. LAPSSET is ranked the global project of the year in opportunity creation not just for the African continent but the whole world," said Kasuku.

The LAPSSET project plan includes a 32-berth port, transportation hubs for rail, highway and international airports in Lamu, Isiolo and Lodwar, an oil pipeline from South Sudan, Uganda and Ethiopia to Lamu Port, an oil refinery and three resort cities in Isiolo, Lamu and Turkana.

[Editor: huaxia]
010020070750000000000000011105521373043741
久青草久青草视频在线观看| 热99re久久国免费超精品首页| 加勒比一区二区三区精品 | 在线不卡av片免费观看| 亚洲AV肉丝网站一区二区无码| 最新午夜男女福利片视频| 在线欧美中文字幕农村电影| 婷婷伊人久久| 国产91九色在线观看| 乱人伦人妻中文字幕| 亚洲伊人天堂| 久久99久久99精品免视看国产成人| 性动态图无遮挡试看30秒| 亚洲精品久久久久国色天香| 亚洲天堂av在线一区| 日本午夜精品视频在线观看| 亚洲精品国男人在线视频| 2020亚洲天堂网| 九九热精品视频免费在线| 人妻丰满熟妇AV无码区乱| 国产在线精品福利大全| 国产精品久久久久免费a∨| 人妻体验按摩到忍不住哀求继续 | 黑人巨大videos极度另类| 国产一区二区三区不卡视频| 熟女人妻aⅴ一区二区三区电影| 亚洲 欧美 唯美 国产 伦 综合| 高潮毛片无遮挡高清视频播放| 在线看无码的免费网站| 国产精品露脸视频观看| 日本a在线播放| 欧美人人干| 一级毛片在线免费视频| 精品国产福利久久久| 看全黄大色黄大片视频| av在线亚洲国产精品| 西欧free性video| 美女视频很黄很a免费| 国产性一交一乱一伦一色一情| 暖暖 免费 高清 日本 在线观看5| 日韩毛片在线视频x|